Get Quick Quote From Supplier
1. Net 35MW of electricity2. Boiler to handle 30 tonnes of Dry (less than 10% MC) Baled agricultural waste per hour3. 2 x 17.5 MW turbines should be considered with 1, 000, 000 lbs of steam per day going to manufacturing process5. Exhaust air cleaning system should be considered6. Entire plant foot print (land area occupied should be considered)7. Mechanised semi automatic feed system should be considered8. Please give the costs in USD biomass, electricity, boiler 160MW(thermal)biomass boilerable to handle 45 t/hr, 35MWe generation steam turbine set turbine